NUCLEAR POWER PLANT LEIBSTADT I NEW OFFICE BUILDING

A modern and dynamic business environment

Client Axpo AG, Baden (principle shareholder of KKL AG)
Project managers Heini M. Bossert, Angela Mizrahi
Time frame
2010 – 2014
Floor area 5,600 m2
Project cost
CHF 30 million
   
Services
  • Client representative and overall project manager for all project phases
  • Monitoring and controlling the costs and project schedule
  • Quality control of the planning team and the contractors
  • Contract and change-order negotiations




To accommodate the increasingly strict legislative requirements, the current user requirements, and the rising number of employees at the KKL Nuclear power plant in Leibstadt, a new office and restaurant building was needed. The building includes training rooms, a personnel restaurant on two floors, a reception area as well as open-plan offices. The main challenges lay in the close coordination with the daily operations of the nuclear power plant, the high security and building requirements as well as the complex internal and official approval processes. We managed the project for the client and reported to the CEO and Board of the KKL in regular intervals.

zurück